Help & Glossary
Everything you need to understand the Connection Intelligence Platform — scoring methodology, connection strategies, key terms, and data sources.
Connection Strategies
Lane A vs Lane B
Connect at full capacity but with a dynamic operating envelope. The BESS can charge/discharge at full power when network conditions allow, but automatically curtails when the network is constrained.
Uses runback systems and real-time monitoring. AusNet sets operating limits that change dynamically based on network loading.
Faster to negotiate if AusNet accepts the envelope approach, but requires more sophisticated control systems and comms infrastructure.
Sites with good network headroom most of the time. The BESS runs unconstrained 80–90 % of the year and curtails only during peak periods.
Connect at a deliberately conservative capacity first (e.g., 1.25 MW instead of 5 MW) to reduce study burden and get energised faster. Then expand later.
"Submit 1.25 MW request but with lead-in feeder/ACR capable of 5 MW. Build and commission at 1.25 MW. Then run normal modelling process and expand to 5 MW once approved."
Fastest path to energisation. Reduced study scope means fewer revision cycles and shorter AusNet assessment.
Sites where getting operational quickly matters more than day-one full capacity. Start earning revenue while the expansion studies proceed in parallel.
Scoring Methodology
How substations are ranked
Feasibility Score
0 – 100
How likely is this substation to receive a connection offer?
Higher = more feasible. A score above 65 indicates a strong candidate.
Acceleration Score
0 – 100
How fast can we get from application to offer?
Higher = faster. Substations with existing Greenwood data packs score significantly higher.
Capex Risk Score
0 – 100 · ⚠ inverse scale
How much will augmentation and connection works cost?
Higher = MORE expensive/risky (inverse — low is better). A high score means higher expected capital expenditure.
Commercial Score
0 – 100
What's the revenue potential vs cost?
Higher = better commercial case. Factors in both revenue upside and cost downside.
Overall Rank
Weighted combination of all four scores
The overall rank is a weighted composite that balances feasibility, speed, cost risk, and commercial viability. Capex risk is inverted (lower cost = higher contribution). The weights are calibrated based on Greenwood's strategic priorities — getting deployable sites first, with a preference for strong commercial cases.
Key Terms Glossary
21 terms
AusNet Connection Process
From site ID to energisation
Realistic timelines calibrated from Greenwood's actual experience across 11 active projects.
Site identification & land lease
Identify target zone substations, secure land near the substation, execute lease.
Pre-feasibility request to AusNet
Formal request letter to AusNet Connections describing the proposed BESS, capacity, and connection point.
Pre-feasibility response
AusNet provides high-level indication of constraints, REFCL status, and likely study requirements.
Data pack request & delivery
Request network data (load traces, SINCAL model, protection settings). This is the single biggest bottleneck. Based on Greenwood's 11-project experience.
Commission steady-state study
Engage a consultant (Powerplant Engineering, APD, or Hanna) to build a SINCAL model and run scenarios.
Submit study to AusNet
Formal submission of completed network study for AusNet technical review.
AusNet review + issues tracker
AusNet assigns a reviewer who logs issues in a tracker. Expect detailed technical questions and requested changes.
Revision cycles
Back-and-forth between consultant and AusNet. The #1 cause of delays. Each round takes 4–8 weeks.
Power quality + dynamic studies (if needed)
Required for larger or more complex connections. Harmonic analysis, transient stability, PSCAD modelling.
Connection application
Formal NER Chapter 5A connection application with all supporting documentation.
Assessment period
AusNet's formal assessment window. Can extend if they raise further issues or require more studies.
Connection offer
AusNet issues a formal connection offer specifying terms, costs, protection requirements, and conditions.
Offer acceptance + detailed design
Review offer, negotiate terms if needed, engage detailed design consultants for protection and metering.
Construction + commissioning
Civil works, BESS installation, switchgear, HV cabling, transformer, comms infrastructure.
Energisation
Final inspections, protection relay commissioning tests, AusNet witness testing, and energisation.
Data Sources
Provenance & confidence
AusNet System Limitation Report 2025
highDetailed thermal, voltage, and protection data for constrained substations. Primary source for scoring.
AusNet Voltage Compliance CSV
mediumVoltage compliance data across the AusNet distribution network. Broader coverage but less depth.
AusNet ZSS Load Trace 2025
highHalf-hourly metering data enabling load profiles, utilisation analysis, and reverse flow detection.
AusNet DAPR 2025
highDistribution Annual Planning Report: export constraints, investment plans, demand forecasts.
Victorian Terminal Station Demand Forecasts (AEMO)
medium10 % POE and 50 % POE demand forecasts out to 2030. Used for growth projections.
Greenwood Project Emails & Comms
highReal-world timeline data, consultant costs, AusNet response times, and issue patterns from Greenwood's active projects.